Project Details
Land Number
J89
Region
BaitWatan, 5th settlement
HOMEi Price
16,500.00 EGP
Neighbour Price
23,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 45% |
| 2 | During Construction | 15% |
| 3 | During Construction | 10% |
| 4 | During Construction | 5% |
| 5 | During Construction | 5% |
| 6 | During Construction | 5% |
| 7 | During Construction | 5% |
| 8 | During Construction | 2.5% |
| 9 | During Construction | 2.5% |
| 10 | During Construction | 2.5% |
| 11 | During Construction | 2.5% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
167 m²
Delivery
Unit Delivery Date
January 2029
Average Unit Price
2,295,000 EGP
Project Location
Map View
BaitWatan, 5th settlement
HOMEi Timeline
License office contract
June 14, 2026
Building permit
June 20, 2026
Excavation permit
October 4, 2026
Construction contract signed
October 5, 2026
Excavation
November 4, 2026
Replacement Layers
December 4, 2026
Plain foundations
January 3, 2027
Reinforced foundations
January 23, 2027
Basement columns
February 22, 2027
Concrete works for the external wall
February 23, 2027
Basement slab
March 14, 2027
Ground floor columns
May 13, 2027
Footings insulation
May 28, 2027
Backfilling over footings
May 28, 2027
Ground floor slab
June 27, 2027
First floor columns
July 27, 2027
First floor slab
August 11, 2027
Second floor columns
September 10, 2027
Second floor slab
September 25, 2027
Third floor columns
October 25, 2027
Third floor slab
November 9, 2027
Roof concrete works
December 9, 2027
Basement walls
January 23, 2028
Wall Building works
January 23, 2028
Ground floor walls
February 2, 2028
First floor walls
February 22, 2028
Second floor walls
March 13, 2028
Third floor walls
April 2, 2028
Roof walls
April 22, 2028
Plumbing main works
May 7, 2028
Electrical final finishes
May 22, 2028
Gypsum Balustrades
June 6, 2028
Plaster and putty
July 11, 2028
Basement Finishing Works
July 11, 2028
Marble works
September 29, 2028
Electrical finishing
October 14, 2028
Security Cameras and Intercom Installation
October 14, 2028
Plumbing finishing
October 29, 2028
Roof Thermal Insulation Works
November 5, 2028
Aluminum & glass works (Krital)
November 13, 2028
Elevator
November 28, 2028
Project handover to the authority
December 28, 2028
Utilities meter installation
January 28, 2029