Project Details
Land Number
1118
Region
The Area 22, El Sadat City
HOMEi Price
4,399.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
| 2 |
|
- | Finished |
| 3 |
|
- | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
August 2025
Average Unit Price
617,558 EGP
Project Location
Map View
The Area 22, El Sadat City
HOMEi Timeline
License office contract
November 15, 2023
Building permit
November 16, 2023
Excavation permit
November 17, 2023
Mining permit
November 18, 2023
Construction contract in progress
November 20, 2023
Construction contract signed
November 24, 2023
Excavation
January 1, 2024
Plain foundations
January 10, 2024
Reinforced foundations
February 1, 2024
Footings insulation
February 15, 2024
Backfilling around foundations
February 25, 2024
Basement columns
March 1, 2024
Basement slab
March 12, 2024
Concrete works for the external wall
March 20, 2024
Wall Building works
May 21, 2025
Basement walls
April 3, 2024
Ground floor columns
April 13, 2024
Ground floor slab
April 30, 2024
Ground floor walls
May 1, 2024
First floor columns
May 10, 2024
First floor slab
May 19, 2024
First floor walls
May 28, 2024
Second floor columns
June 3, 2024
Second floor slab
June 18, 2024
Second floor walls
July 1, 2024
Third-floor addition permit
August 1, 2024
Third floor columns
August 11, 2024
Third floor slab
August 22, 2024
Third floor walls
August 21, 2024
Roof extension license
December 1, 2024
Roof concrete works
January 1, 2025
Roof walls
February 2, 2025
Wooden door frames
March 2, 2025
Plumbing works
April 17, 2025
Electrical works
April 20, 2025
Plaster and putty
June 10, 2025
Marble works
June 11, 2025
Aluminum & glass works (Krital)
June 12, 2025
Utilities meter installation
July 1, 2025
Elevator
August 30, 2025
Project handover to the authority
August 30, 2025