Project Details
Land Number
1168
Region
The Area 22, El Sadat City
HOMEi Price
5,600.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
| 2 |
|
- | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
July 2026
Average Unit Price
803,250 EGP
Project Location
Map View
The Area 22, El Sadat City
HOMEi Timeline
License office contract
July 15, 2024
Building permit
July 18, 2024
Excavation permit
July 20, 2024
Mining permit
July 21, 2024
Construction contract in progress
July 22, 2024
Construction contract signed
July 23, 2024
Excavation
August 1, 2024
Plain concrete
August 10, 2024
Reinforced concrete
August 15, 2024
Footings insulation
August 20, 2024
Backfilling around foundations
September 2, 2024
Basement columns
September 3, 2024
Basement slab
September 4, 2024
Basement walls
September 5, 2024
Ground floor columns
September 22, 2024
Ground floor slab
October 2, 2024
Ground floor walls
October 2, 2024
First floor columns
October 22, 2024
High-quality execution of first-floor columns, with precise reinforcement detailing and concrete casting in accordance with engineering standards.
First floor slab
November 2, 2024
Second floor columns
November 22, 2024
Second floor slab
December 2, 2024
Third-floor addition permit
March 20, 2025
Third floor columns
June 16, 2025
Third floor slab
June 23, 2025
First floor walls
March 11, 2025
Roof extension license
July 21, 2025
Roof concrete works
July 29, 2025
Second floor walls
March 6, 2025
Third floor walls
September 16, 2025
Roof walls
September 16, 2025
Electrical works
December 30, 2025
Wall Building works
November 15, 2025
Concrete works for the external wall
November 1, 2025
Wooden door frames
November 13, 2025
Aluminum & glass works (Krital)
January 3, 2026
Plumbing works
December 30, 2025
Plaster and putty
December 31, 2025
Marble works
February 1, 2026
Elevator
March 1, 2026
Project handover to the authority
June 1, 2026
Utilities meter installation
July 1, 2026