Project Details
Land Number
1295
Region
The Area 29, El Sadat City
HOMEi Price
9,200.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
May 2026
Average Unit Price
1,296,000 EGP
Project Location
Map View
The Area 29, El Sadat City
HOMEi Timeline
License office contract
October 5, 2024
Submitting the license
October 10, 2024
Excavation permit
October 15, 2024
Mining permit
October 16, 2024
Obtaining a construction insurance certificate
October 20, 2024
Extracting a Building water meter
October 20, 2024
Construction contract in progress
November 19, 2024
Construction contract signed
November 19, 2024
Excavation
November 20, 2024
Reinforced concrete
December 2, 2024
Plain concrete
November 27, 2024
Footings insulation
December 15, 2024
Backfilling around foundations
January 26, 2025
Basement columns
February 4, 2025
Basement slab
February 5, 2025
Concrete works for the external wall
February 10, 2025
Wall Building works
February 17, 2025
Ground floor columns
February 25, 2025
Ground floor slab
March 4, 2025
Basement walls
March 4, 2025
First floor columns
March 22, 2025
First floor slab
March 29, 2025
Second floor columns
April 16, 2025
Second floor slab
April 23, 2025
Ground floor walls
May 11, 2025
First floor walls
May 21, 2025
Second floor walls
May 28, 2025
Third-floor addition permit
August 8, 2025
Third floor columns
August 9, 2025
Third floor slab
August 16, 2025
Third floor walls
September 3, 2025
Roof extension license
September 3, 2025
Roof concrete works
December 2, 2025
Roof walls
December 27, 2025
Plumbing works
January 4, 2026
Electrical works
January 4, 2026
Plaster and putty
January 8, 2026
اعمال المحاره الدخليه للسلم الرئيسي للمبني
Marble works
February 17, 2026
Aluminum & glass works (Krital)
February 17, 2026
Elevator
February 22, 2026
Project handover to the authority
April 2, 2026
Utilities meter installation
May 1, 2026