Project Details
Land Number
1230
Region
The Area 22, El Sadat City
HOMEi Price
7,300.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 15% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
| 5 | During Construction | 5% |
| 6 | During Construction | 5% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
July 2026
Average Unit Price
1,053,000 EGP
Project Location
Map View
The Area 22, El Sadat City
HOMEi Timeline
License office contract
January 25, 2025
Receiving the license
January 30, 2025
Excavation permit
January 31, 2025
Construction contract in progress
February 1, 2025
Construction contract signed
February 4, 2025
Excavation
February 8, 2025
Basement walls
May 22, 2025
Plain concrete
February 13, 2025
Reinforced concrete
February 28, 2025
Footings insulation
March 1, 2025
Backfilling over footings
March 3, 2025
Basement columns
March 7, 2025
Fence columns
March 16, 2025
Basement slab
June 25, 2025
Ground floor columns
July 6, 2025
Ground floor slab
July 13, 2025
First floor columns
July 20, 2025
First floor slab
November 10, 2025
Second floor columns
November 17, 2025
Second floor slab
June 17, 2025
Submitting third-floor extension license
December 1, 2025
Receiving third-floor extension license
April 13, 2026
Third floor columns
September 22, 2025
Third floor slab
October 7, 2025
Roof extension license
April 13, 2026
Roof concrete works
January 12, 2026
Ground floor walls
September 12, 2025
First floor walls
April 8, 2026
Second floor walls
March 14, 2026
Wall Building works
March 14, 2026
Third floor walls
March 24, 2026
Roof walls
April 3, 2026
Wooden door frames
April 3, 2026
Plumbing main works
April 8, 2026
Electrical final finishes
April 15, 2026
Plaster and putty
June 1, 2026
Marble works
June 11, 2026
Plumbing finishing
June 11, 2026
Aluminum & glass works (Krital)
June 21, 2026
Electrical finishing
June 26, 2026
Elevator
July 10, 2026