Project Details
Land Number
565
Region
The Area 21, El Sadat City
HOMEi Price
8,000.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 15% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
| 5 | During Construction | 5% |
| 6 | During Construction | 5% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
April 2026
Average Unit Price
1,161,000 EGP
Project Location
Map View
The Area 21, El Sadat City
HOMEi Timeline
License office contract
October 17, 2024
Building permit
October 24, 2024
Excavation permit
November 7, 2024
Mining permit
November 9, 2024
Construction contract in progress
November 10, 2024
Construction contract signed
November 11, 2024
Excavation
November 12, 2024
Plain foundations
November 13, 2024
Reinforced concrete
November 27, 2024
Footings insulation
December 15, 2024
Backfilling over footings
February 2, 2025
Basement columns
February 4, 2025
Basement slab
February 25, 2025
Basement walls
March 4, 2025
Concrete works for the external wall
March 5, 2025
Wall Building works
March 9, 2025
Ground floor columns
March 14, 2025
Ground floor slab
March 22, 2025
Ground floor walls
March 29, 2025
First floor columns
April 5, 2025
First floor walls
April 10, 2025
First floor slab
April 16, 2025
Second floor columns
April 23, 2025
Second floor walls
April 24, 2025
Second floor slab
May 11, 2025
Third-floor addition permit
May 12, 2025
Third floor columns
May 28, 2025
Third floor walls
May 31, 2025
Third floor slab
June 18, 2025
Roof extension license
September 3, 2025
Roof concrete works
December 9, 2025
Roof walls
December 27, 2025
Electrical works
February 17, 2026
Plumbing works
February 20, 2026
Plaster and putty
February 22, 2026
Marble works
February 24, 2026
Aluminum & glass works (Krital)
February 24, 2026
Elevator
March 15, 2026
Project handover to the authority
March 16, 2026
Utilities meter installation
April 1, 2026