Project Details
Land Number
744
Region
The Area 21, El Sadat City
HOMEi Price
2,999.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
| 2 |
|
- | Finished |
| 3 |
|
- | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
128 m²
Delivery
Unit Delivery Date
April 2025
Average Unit Price
438,683 EGP
Project Location
Map View
The Area 21, El Sadat City
HOMEi Timeline
License office contract
January 5, 2023
Building permit
January 15, 2023
Extracting a Building water meter
January 17, 2023
Obtaining a construction insurance certificate
January 22, 2023
Excavation permit
January 27, 2023
Mining permit
January 28, 2023
Construction contract in progress
January 29, 2023
Construction contract signed
January 30, 2023
Excavation
January 31, 2023
Plain foundations
February 1, 2023
Reinforced foundations
February 5, 2023
Footings insulation
February 17, 2023
Backfilling over footings
February 18, 2023
Basement columns
March 13, 2023
Basement slab
March 15, 2023
Ground floor columns
March 25, 2023
Basement walls
April 1, 2023
Ground floor slab
April 1, 2023
Ground floor walls
April 10, 2023
Concrete works for the external wall
April 15, 2023
Wall Building works
April 20, 2023
First floor columns
April 25, 2023
First floor slab
May 5, 2023
First floor walls
May 10, 2023
Second floor columns
May 15, 2023
Second floor slab
May 27, 2023
Second floor walls
June 10, 2023
Third-floor addition permit
January 1, 2024
Obtaining an insurance certificate for a third-floor extension
January 5, 2024
Third floor columns
January 10, 2024
Third floor slab
January 25, 2024
Third floor walls
February 5, 2024
Roof extension license
February 25, 2024
Obtaining a roof insurance certificate
March 1, 2024
Roof concrete works
March 5, 2024
Roof walls
March 20, 2024
Wooden door frames
April 1, 2024
Electrical works
April 15, 2024
Plumbing works
April 20, 2024
Plaster and putty
May 1, 2024
Finishing works
January 20, 2025
Marble works
January 25, 2025
Entrance finishing
February 8, 2025
Aluminum & glass works (Krital)
February 9, 2025
Façades
February 17, 2025
Elevator
February 18, 2025
Project handover to the authority
March 23, 2025
Utilities meter installation
April 1, 2025