Project Details
Land Number
201
Region
The Area 35, El Sadat City
HOMEi Price
2,800.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 25% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
185 m²
Delivery
Unit Delivery Date
August 2023
Average Unit Price
393,525 EGP
Project Location
Map View
The Area 35, El Sadat City
HOMEi Timeline
License office contract
July 26, 2022
Building permit
August 1, 2022
Excavation permit
September 1, 2022
Construction contract in progress
September 4, 2022
Construction contract signed
September 5, 2022
Excavation
September 8, 2022
Plain concrete
September 10, 2022
Reinforced foundations
September 11, 2022
Footings insulation
September 25, 2022
Backfilling around foundations
October 1, 2022
Basement columns
October 3, 2022
Basement slab
October 11, 2022
Basement walls
October 19, 2022
Ground floor columns
November 8, 2022
Wall Building works
November 20, 2022
Ground floor slab
December 6, 2022
First floor columns
December 12, 2022
First floor slab
December 27, 2022
Ground floor walls
December 30, 2022
First floor walls
January 6, 2023
Second floor columns
January 10, 2023
Second floor slab
January 20, 2023
Second floor walls
February 1, 2023
Third-floor addition permit
February 1, 2023
Obtaining an insurance certificate for a third-floor extension
February 2, 2023
Third floor columns
February 15, 2023
Third floor slab
February 28, 2023
Third floor walls
March 2, 2023
Roof extension license
March 4, 2023
Obtaining a roof insurance certificate
March 9, 2023
Roof concrete works
March 23, 2023
Roof walls
April 1, 2023
Wooden door frames
April 10, 2023
Electrical works
April 27, 2023
Plumbing works
April 28, 2023
Plaster and putty
May 7, 2023
Marble works
July 22, 2023
Aluminum & glass works (Krital)
July 23, 2023
Elevator
August 10, 2023
Project handover to the authority
August 12, 2023
Utilities meter installation
August 23, 2023