Project Details
Land Number
1229
Region
The Area 22, El Sadat City
HOMEi Price
9,000.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 10% |
| 3 | During Construction | 10% |
| 4 | During Construction | 10% |
| 5 | During Construction | 5% |
| 6 | During Construction | 5% |
| 7 | During Construction | 5% |
| 8 | During Construction | 5% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
August 2028
Average Unit Price
1,282,500 EGP
Project Location
Map View
The Area 22, El Sadat City
HOMEi Timeline
License office contract
April 20, 2026
Building permit
May 1, 2026
Excavation permit
August 29, 2026
Construction contract in progress
October 26, 2026
Construction contract signed
October 26, 2026
Excavation
October 28, 2026
Plain concrete
November 7, 2026
Reinforced concrete
November 8, 2026
Basement columns
December 7, 2026
Basement walls
December 22, 2026
Basement slab
January 16, 2027
Ground floor columns
February 15, 2027
Ground floor walls
March 2, 2027
Ground floor slab
March 27, 2027
Footings insulation
April 26, 2027
Backfilling over footings
April 28, 2027
First floor columns
May 11, 2027
First floor walls
May 26, 2027
First floor slab
June 20, 2027
Second floor columns
July 20, 2027
Second floor walls
August 4, 2027
Second floor slab
August 29, 2027
Third floor columns
September 28, 2027
Third floor walls
October 13, 2027
Third floor slab
November 7, 2027
Roof concrete works
December 7, 2027
Roof walls
December 17, 2027
Concrete works for the external wall
January 31, 2028
Wall Building works
February 1, 2028
Plumbing main works
February 15, 2028
Electrical final finishes
March 1, 2028
Plaster and putty
March 16, 2028
Marble finishing
May 15, 2028
Electrical finishing
June 4, 2028
Plumbing finishing
June 14, 2028
Aluminum & glass works (Krital)
June 24, 2028
Elevator
July 9, 2028
Project handover to the authority
August 9, 2028
Utilities meter installation
August 10, 2028