Project Details
Land Number
333
Region
The Rawda, El Sadat City
HOMEi Price
8,000.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 10% |
| 3 | During Construction | 10% |
| 4 | During Construction | 10% |
| 5 | During Construction | 10% |
| 6 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
133 m²
Delivery
Unit Delivery Date
May 2029
Average Unit Price
1,147,500 EGP
Project Location
Map View
The Rawda, El Sadat City
HOMEi Timeline
License office contract
February 20, 2026
Submitting the license
March 1, 2026
Receiving the license
March 1, 2026
Excavation permit
July 29, 2026
Mining permit
August 2, 2026
Construction contract in progress
September 1, 2026
Construction contract signed
September 10, 2026
Excavation
September 27, 2026
Plain foundations
October 12, 2026
Reinforced concrete
November 1, 2026
Basement columns
November 26, 2026
Basement walls
December 31, 2026
Basement slab
February 9, 2027
Ground floor columns
March 31, 2027
Ground floor walls
April 25, 2027
Ground floor slab
May 20, 2027
Footings insulation
June 19, 2027
Backfilling over footings
June 19, 2027
First floor columns
July 9, 2027
First floor walls
July 24, 2027
First floor slab
September 2, 2027
Second floor columns
September 22, 2027
Second floor walls
October 7, 2027
Second floor slab
November 6, 2027
Third floor columns
December 6, 2027
Third floor walls
December 16, 2027
Third floor slab
January 5, 2028
Roof extension license
January 29, 2028
Roof room columns
January 30, 2028
Roof walls
February 14, 2028
Roof room slab
March 10, 2028
Wall Building works
April 4, 2028
Plumbing main works
April 24, 2028
Electrical final finishes
May 9, 2028
Plaster and putty
May 19, 2028
Marble finishing
August 11, 2028
Electrical finishing
September 16, 2028
Plumbing finishing
October 1, 2028
Aluminum & glass works (Krital)
October 16, 2028
Elevator
November 15, 2028
Project handover to the authority
January 14, 2029
Utilities meter installation
May 1, 2029