HOMEi Timeline
License office contract
November 28, 2025
Submitting the license
December 15, 2025
Receiving the license
January 25, 2026
Excavation permit
February 15, 2026
Construction contract in progress
February 16, 2026
Construction contract signed
February 17, 2026
Excavation
March 9, 2026
Plain foundations
May 8, 2026
Reinforced foundations
May 8, 2026
Basement columns
June 7, 2026
Basement slab
July 22, 2026
Ground floor columns
August 21, 2026
Ground floor slab
September 5, 2026
Footings insulation
October 4, 2026
Backfilling around foundations
October 5, 2026
First floor columns
October 15, 2026
First floor slab
October 30, 2026
Second floor columns
November 29, 2026
Second floor slab
December 14, 2026
Submitting third-floor extension license
December 15, 2026
Third floor columns
January 13, 2027
Third floor slab
January 28, 2027
Roof extension license
January 30, 2027
Roof concrete works
February 27, 2027
Fence columns
March 14, 2027
Basement walls
April 13, 2027
Ground floor walls
May 3, 2027
First floor walls
May 23, 2027
Second floor walls
June 12, 2027
Third floor walls
July 2, 2027
Roof walls
July 22, 2027
Wooden door frames
August 6, 2027
Plumbing main works
August 21, 2027
Electrical final finishes
September 5, 2027
Plaster and putty
September 20, 2027
Electrical finishing
January 17, 2028
Plumbing finishing
January 17, 2028
Marble works
January 18, 2028
Aluminum & glass works (Krital)
January 18, 2028
Elevator
January 19, 2028
Project handover to the authority
January 20, 2028
Utilities meter installation
January 30, 2028