Project Details
Land Number
1528
Region
The Area 29, El Sadat City
HOMEi Price
8,100.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 15% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
| 5 | During Construction | 5% |
| 6 | During Construction | 5% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
195 m²
Delivery
Unit Delivery Date
May 2027
Average Unit Price
1,120,500 EGP
Project Location
Map View
The Area 29, El Sadat City
HOMEi Timeline
License office contract
July 22, 2025
Submitting the license
November 10, 2025
Receiving the license
April 1, 2026
Excavation permit
November 16, 2025
Mining permit
November 16, 2025
Construction contract in progress
November 17, 2025
Construction contract signed
November 18, 2025
Excavation
November 20, 2025
Plain foundations
December 1, 2025
Reinforced foundations
December 10, 2025
Footings insulation
December 15, 2025
Backfilling around foundations
December 16, 2025
Basement columns
December 17, 2025
Basement slab
January 7, 2026
Ground floor columns
January 14, 2026
Ground floor slab
February 4, 2026
First floor columns
February 14, 2026
First floor slab
March 7, 2026
Second floor columns
March 14, 2026
Second floor slab
March 29, 2026
Submitting third-floor extension license
March 30, 2026
Third floor columns
July 4, 2026
Third floor slab
July 19, 2026
Roof extension license
July 20, 2026
Fence columns
July 20, 2026
Roof concrete works
July 21, 2026
Basement walls
November 24, 2026
Ground floor walls
December 4, 2026
First floor walls
December 14, 2026
Second floor walls
December 24, 2026
Third floor walls
January 3, 2027
Roof walls
January 13, 2027
Wooden door frames
January 18, 2027
Plumbing main works
January 25, 2027
Electrical final finishes
February 1, 2027
Plaster and putty
April 2, 2027
Plumbing finishing
April 9, 2027
Aluminum & glass works (Krital)
April 12, 2027
Marble finishing
April 17, 2027
Electrical finishing
April 24, 2027
Elevator
May 2, 2027
Project handover to the authority
May 5, 2027
Utilities meter installation
May 8, 2027